Powering your community
Information about improvements to the electricity network
SP Energy Networks is undertaking work to upgrade our electricity infrastructure in your area, and as part of that, we are about to carry out significant works from Cupar Grid supply point, through the town, along the A91, through Dairsie and onto Guardbridge – see attached map.
We have worked closely with the local authority in planning this project to minimise disruption to the local community where possible.
Traffic restriction orders will be in place during the works, and we kindly ask you to follow any instructions. We apologise for any inconvenience caused and will make every effort to minimise impact to the community while we carry out reinforcements to the local network.
The main bulk of the work will take place:
From the 26th of September 2024 until August 2025
For further information and what to expect download the customer communications letter
For emergencies call Walker & Watts on
For updates email Walker & Watts on
Below is a summary of the works that will take place and their percentages complete
Please note that the dates below are indicative to the programme, however, if there are challenges with conditions on the routes, the dates may be subject to change.
Moathill Road
Total Length 767m
Completion: 53%

100%
Moathill Road Phase 1 - 403m
Start End
06/10/2024    
   
13/10/2024

0%
Moathill Road Phase 2 - Lady Wynd & Northbound - 10m
Start End
26/02/2025       01/03/2025

0%
Moathill Road Phase 3 - 354m
Start End
27/02/2025 
     23/03/2025
East Burnside to A91
Total Length 5600m
Completion: 33%

0%
East Burnside - 310m
Start End
31/01/2025    
   
27/02/2025

0%
East Road - 876m
Start End
21/02/2025      10/04/2025

67%
East Bridge - 120m
Start End
04/04/2025       27/04/2025

0%
A91 - East Rd Roundabout to Cottage Bank - 880m
Start End
14/11/2024                             

0%
A91 - Mainstreet Dairsie to Dairsie RA - 344m
Start End
14/11/2024                             

0%
Mainstreet Dairsie - 655m
Start End
14/11/2024                             

100%
A91- Acess Road to FoodHall - 1000m
Start End
06/11/2024                                  

22%
A91 - Cottage Bank to Todhall Farm - 1400m
Start End
14/11/2024                             
Statheden Park to Drum Rd Cupar Muir - Westfield Ave Jct
Total Length 1000m
Completion: 74%

77%
Westfield Road - 843m
Start End
15/11/2024                  16/02/2025          

0%
Drum Rd Cupar Muir to Westfield Rd - 53m
Start End
      21/03/2025          30/03/2025                      

0%
Statheden Park to Drum Rd Cupar Muir - 20m
Start End
14/11/2024                             
A91 Roundabout A914
to Main Street
Total Length 4500m
Completion: 7%

77%
Main Street Guardbridge- 843m
Start End
          22/10/2024                  16/02/2025          

0%
Guardbridge - 20m
Start End
      09/02/2025          12/02/2025                      

0%
Cupar Road - 257m
Start End
    10/02/2025                  01/03/2025     

0%
U118 Jc to Cupar Road Guardbridge - 240m
Start End
          27/02/2025                  14/03/2025          

0%
U118 JC to Cupar Road Guardbridge 1236m
Start End
    12/03/2025                  01/05/2025                   

0%
Clayton Caravan Park to U118Jc - 570m
Start End
        20/04/2025        18/05/2025                     

0%
A91 - Dairsie RA to Clayton Caravan Park - 125m
Start End
          16/05/2025                  28/05/2025          

0%
A91 - Dairsie RA to Clayton Caravan Park - 560m
Start End
      25/05/2025          18/06/2025                      
Westfield Avenue
Total Length 240m
Completion: 45%

100%
Westfield Ave Phase 1 - 108m
Start End
                       07/11/2024             16/11/2024                     

0%
Westfield Avenue Phase 2 - 138m
Start End
                    14/02/2025         28/02/2025                    
Video Progress - 10 December 2024
The video shows the progress of the works and the types of activities taking place for works

